Answer / modipraveen
Dear Suhil,
There is no extra bar will be provided for slab "but in
design extra load/further extra floor will considered",
Distance of bent bar are depends on span its varies to L/3
to L/7, and Slab's reinforcement will continue to Chajja It
may main or secondary/distribution rods, concept it to take
chajja's load on slab/beam, its just over hang the slab...
| Is This Answer Correct ? | 4 Yes | 4 No |
Answer / galanna
There is no extra bar will be provided for slab "but in
design extra load/further extra floor will considered",
Distance of bent bar are depends on span its varies to L/3
to L/7, and Slab's reinforcement will continue to Chajja It
may main or secondary/distribution rods, concept it to take
chajja's load on slab/beam, its just over hang the slab...
| Is This Answer Correct ? | 0 Yes | 1 No |
what are the standard & nominal size of brick
What quantity of 1.0 m3 bricks required?
coarse sand has a fineness modulus in range of
What is the full form of APVC Pipe?
component parts of a weir
4 Answers Infosys, L&T, Zamil Steel,
what are the differences between Tie beam, Ground beam and strap beam. thanks
Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish
What is difference between nominal mix and design mix?
what is the significance of soundness test in Cement? and how is it done??
1 Answers Biltech Building Elements, Student,
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.
How can we calculate the cement Quantity in M25?
2 Answers JK Associates, Vardhman, Wave Infratech,
cement mortar 1:6 explain the cement and sand coefficient calculation?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)