200sq.ft of slab and thickness is 6" in that how much cement
are required(bags), sand & aggregates are in cu.m, choose
grade of concrete is m20.
Answers were Sorted based on User's Feedback
Answer / shivang
cement bags= 23 bags=((1/5.5)*1.57))/0.035
Sand = 1.21 m3= ((1.5/5.5)/1.57))*2.83
Aggregates = 2.42 m3= ((3/5.5)/1.57))*2.83
| Is This Answer Correct ? | 6 Yes | 0 No |
Answer / single ravi
200*.5=100cft/35.32=2.83cum
2.83*6.5=18.39bags
18.35*50=919.75kg of cement required for the given problem
| Is This Answer Correct ? | 6 Yes | 2 No |
Answer / md afroz alam
22 bags of cement
42 cft sand
83 cft agg, 20mm size
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / guest
Cement bag is 20 Nos
Sand 50 cft
Aggregates 100 cft
| Is This Answer Correct ? | 0 Yes | 1 No |
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
At what point does a circle start losing area when being flattened?
how do we design mix ratio?
what cement consumction plaster 15mm think per sqmt 1:3&1:6 how much kg.
difference between specification and method of statement
Hi frens, i need MahaGenco previous exam papers of civil engineering as well recent MahaTransco exam papers? If anybody having it plz help or at least i want to know which subject shuold i focus for studies? Thanks in advance.
koi bta sakta ha ka steel ko calculate krna ka full mathod pls
what is called fck
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?
what is the difference between sill beam,Tie beam and plinth beam?
10. Do you remain in good relationship with your previous employer / company where you no longer work /?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)