200sq.ft of slab and thickness is 6" in that how much cement
are required(bags), sand & aggregates are in cu.m, choose
grade of concrete is m20.
Answer Posted / shivang
cement bags= 23 bags=((1/5.5)*1.57))/0.035
Sand = 1.21 m3= ((1.5/5.5)/1.57))*2.83
Aggregates = 2.42 m3= ((3/5.5)/1.57))*2.83
Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
material used for mendrel use to bend epoxy coated rebar
sir how can we find the cement and sand required for making 4" drop
Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......
What is labor and material payment bond?
What does civil engineering mean?
What is the worlds largest concrete dam?
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
What is min thickness,min grade of conc & age of PQC ?
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
How much cement,sand,bricks and water needed for 1square metre brick work?
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
What are wooden shingles?
Define What is the best type of wood glue?
What quantity of 1.0 m3 bricks required?
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.