Answer / gopi
back Filling:
after completing foundation or any structure,doing that gape filling or extra area
Refilling:
temporary or wrong excavation filled all excavated area
| Is This Answer Correct ? | 4 Yes | 5 No |
Answer / sjtbehera
Backfilling is done after a structure complete its ground construction. Refilling means cutting then immediate filling but you go without technical both are same meaning.
| Is This Answer Correct ? | 2 Yes | 5 No |
Answer / sha
The excavated sand filling called back filling..and filling
red earth from out side is called refilling
| Is This Answer Correct ? | 2 Yes | 9 No |
What is a BBS?Find out the cutting length for a 600*600 foundation with 50 mm cover
Please tell me 1 Sqm Steel 14mm center to center .200,.200
I Have concrete mix with 440kg opc and having 37 mpa strengh in 7days while in 28 days only 42mpa can anybody tell me the reason for the same.
What is bylayer?
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
what is the cut length for Fe 500?
What is code for designing a sheet pile?
What is the capacity of Maharashtra in power generation by winds?
5 Answers MPSC, State Bank Of India SBI,
how to calculate triangular ring cutting length
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
1.how to calculate the nails qty in shuttering of column,beam, shear wall. 2.how control the binding wire wastage in building project. 3.
how to take quantity of steel per cum in columns
2 Answers ERRA, Skyline Builders,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)