Answer / mughalsab
if i dont raised at mid ponit of slab so when we poured concrete then the slab is sag at mid point due to its own weight therefore we raised at mid point so when concrete is poured then the slab is going to its corect position.
| Is This Answer Correct ? | 9 Yes | 1 No |
Answer / bharat gurav
because at middle point act point load & share force act at
L/4 so extra steel r provided...............but at mid-span
no provide extra steel due 2 sla raise 10-12mm
| Is This Answer Correct ? | 1 Yes | 4 No |
Rigid pavement Load in tyre preesure It Means KG
whaat is the difference between opc and ppc
Which is stronger solid steel rod or hollow steel pipe?
wat is the size of fine aggregate & coarse aggregate?
How many weight per 1meter cube of concrete for column.
Difference between tension and compression zone
Which one is the main bar in a square slab (2m x 2m)
Is 456 revised lastly in which year? & What are the revisions?
Define block?
how to calculate the quantity of material in 1 cubic meter Concrete?
What is a deep beam ? Explain ?
what is the productivity in aluminium shuttering per day
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)