Answer / bharath
need to go for 3, 7 & 28 days. And care to be taken in WC
ratio & Cube filling process while concrete process
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / shashank
wait till 28 days result will come some time 7 days result
will fail due to poor workmanship will pouring the cube
| Is This Answer Correct ? | 6 Yes | 1 No |
Answer / riaz
The actual result come after 28 days but it still depend on weather condition
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / ratheesh
If 7th day cube fail, we have to wait 28 day cube result.
Should be use skilled labours...then wont get any cube failure.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / mohd. haider
By checking the strength of member by core cutting or remote hammer test. If strength is OK. Than no problem otherwise take action seriously.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / amar kantak
RECHECK THE STRENGTH AND WATER , CEMENT , COARSE & FINE GRAVEL
QUALITY.
| Is This Answer Correct ? | 1 Yes | 1 No |
Answer / pk priyadarshi
in three numbers cube one number cube discard and take two numbers cubs average strength if strength is found as per required that is ok
| Is This Answer Correct ? | 0 Yes | 0 No |
Hi frens, i need MahaGenco previous exam papers of civil engineering as well recent MahaTransco exam papers? If anybody having it plz help or at least i want to know which subject shuold i focus for studies? Thanks in advance.
Is there any codal provision stating the actual diameter for chair bars?
Define What is the distance between railway tracks?
where are using of one way slab ?
How much bricks, cement
how we can prevent freshly laid concrete from rain ,, What the plastering thickness for a) inner brickwork b) outer brickwork c) beams & slabs
how to calculate the cement, sand, coarse aggregate required for one cubic meter of concrete?
how to calculate the strength of rebound hammer test reading in building construction ?
Define What is rigging?
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
where bitumen emulsion is used
what are the types of bridges respective to the span ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)