Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How much steel and concrit required in 1000 square feet
slab?

Answers were Sorted based on User's Feedback



How much steel and concrit required in 1000 square feet slab?..

Answer / shivaji yadav

Steel = .12*1000/10.76 *90 = 1003.72Kg = 1.0 MT

Concrete = .12*1000/10.76 = 11.15 Cum

Is This Answer Correct ?    19 Yes 10 No

How much steel and concrit required in 1000 square feet slab?..

Answer / swaminathan

Assume Slab Thickness 120 & Steel 80kg/Cum

Steel = .12*1000*80 = 9600 kg = 9.6 MT

Concrete = .12*1000 = 120 Cum

Is This Answer Correct ?    12 Yes 23 No

Post New Answer

More Civil Engineering Interview Questions

How many cement bags of 50Kgs will be required for 2600sqft terrace with thickness of 5".

7 Answers  


can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...

0 Answers   Golden Bridge Contracting,


1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.

0 Answers  


1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?

0 Answers   Sona,


what is Quality Reporting?

6 Answers   NCC,


1) why bent up are provided at l/4 or l/5 distance not at l/8or l/10? 2) why extras are provided in beams at top and why upto 0.3l distance max.? 3) why chairs are provided in two way slab?

1 Answers   L&T,


What is difference between code and standard and specification?

0 Answers  


From which end do you start deshuttering in a) cantilever portion b) simply supported portion

3 Answers   ITC Infotech,


if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?

0 Answers  


How many kilo of binding wire required for one ton of reinforcemet steel binding?

17 Answers   ECCI, L&T, Shri Janani Homes,


Which pavement is advisable in India?(Flexible or Rigid)

6 Answers  


What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?

0 Answers   Shell,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)