Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is the meaning of sleeves in reinforced concrete????.
where its coming???.



what is the meaning of sleeves in reinforced concrete????. where its coming???...

Answer / nravindran

Sleeves means to avoid the bonding in concrete to
reinforcement, Because when you are going to start
construction joint that part we want to provide sleeves,
In pile, where ever we are going to leave dowels in that
part

Is This Answer Correct ?    3 Yes 10 No

Post New Answer

More Civil Engineering Interview Questions

what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?

0 Answers  


What is binding spacing of the rebars at lapping zones.

0 Answers  


Can anyone tell me the salary and job profile of transportation engineers/transport engineer?

1 Answers  


If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?

0 Answers   Talib and Shamsi Constructions,


how to convert kg/m3 to cu ft

1 Answers   Ace Group,


WHAT IS THE MINIMUM WATER CONTENT PER ONE BAG CEMENT FOR M20 CONCRETE

5 Answers  


Respected Sir, I am from a hilly place called Darjeeling ,I have constructed house of 9 column out of which 4 of the column is under water , i have put rcc slab on top and on top of the rcc slab i have construced two room house with bricks and light roof , now i am planning to change the light roof with rcc slab for the two room, my main concern is will the column under water will hold the load of the new rcc slab coz it already 10 to 12 yrs old , i dont know what to do , can u advice me regarding this matter, weather to leave the upper floor roof light or make it rcc slab.(If i put the slab , it will require 45bags of cement and u calculate how much of steel and sand and pebbles) thanks with regard Anand

2 Answers  


How to Calculate no.of bricks in 1sq.mtr

3 Answers   SADC,


how to tie 10 legged stirrups

0 Answers   Khan,


What is the bar bending schedule

1 Answers   TCIL,


Define What is unit weight of normal concrete?

0 Answers  


what,s the clear cover of beam,slab,column,lintel and foundation?

36 Answers   Max Myanmar, Spar Geo Infra, Yashwant Construction‎,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)