1)define the critical items in rcc framed G+18 bldg. as Cr Activity 1,Cr Activity 2,Cr Activity 3...

Answer / noor

The logic behind the MSP and primavera is CPM(CRITICAL PATH METHOD). FS,SF, FFand SS are used in relationship assigning the successors and predecessors for activities .

Is This Answer Correct ?    2 Yes 0 No

1)define the critical items in rcc framed G+18 bldg. as Cr Activity 1,Cr Activity 2,Cr Activity 3...

Answer / prashanth

1.Sub structural works
Mass excavation,Footing works,Plinth works,backfilling
(required),Drainages,Plumbing works
2.Super structure works
Columns,Slab,block work,joinery,plastering,Tiling works.
3.Fire line,water line,Electrical works.
4.Snags/Punch list.
5.Final handover.

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

How to calculate density(dry & bulk) of sand from Sp. ravity value of sand. eg. G=2.5

1 Answers  


what is diffreant between the english bond&flamish bond

2 Answers  


what is mean by compressive strength

3 Answers  


what is tmc ,term is used in measureing water, pls tell me 1 tmc = how many litres?

18 Answers   College School Exams Tests, Irrigation, IT Consulting Services, IVRCL,


Moisture content calculation for diff mix ratio's ??

0 Answers  






What is specific gravity & how it is calculated

2 Answers  


calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum

4 Answers   Gresp, L&T,


how much quantity of mortar required for cement pointing work?

0 Answers   City Corporation, Pragya Construction, Simplex,


What does 'M' stands for in M24 bolt ?

2 Answers   Rites,


What is relation between weight and grade of concrete?

1 Answers  


RCC colums of 15"X9" each, roof height 10.5'ft, total pillars 12 nons. Span between pillar to pillar is 14/20/20 length wise and 17/14 width wise. Total Slab area 2400 sft and plinth area is 1900 sft. beams are 12"X12". kindly calculate load factor per sqft.

2 Answers   ABS Construction, L&T,


by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)