Why would an Engineer consider combining FEEDBACK and
FEEDFORWARD control in some applications?
Answers were Sorted based on User's Feedback
Answer / gonzales
In boiler when tripple element controlling required
Is This Answer Correct ? | 4 Yes | 2 No |
Answer / nikhil
In some applications, the compensation provided by feedback control is not sufficient.
Also, the feedforward control is faster but it is difficult to predict all the manipulated variables.
Hence a combination of both is used.
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / r.murugan
Feed forward control required three inputs like drum level
control (steam flow,drum level,feedwater flow
closed loop control with feedback only applicable
Is This Answer Correct ? | 1 Yes | 0 No |
What is the constant voltage unit?
HOW CREATED LP & HP PRESURES IN DRUM FOR DRUM LEVEL MEASUREMENT!
what is RTV function in in process control?
what is cascade loop and how it work and why it used instead of PID single loop? In cascade, Which loop is faster and slower? Please explain with loop drawing and example...
How will you measure surface temperature of SUN?
Regarding , there is an air cooler which control the fans(50% of AV FANS) by temperature in outlet , and the louver of Air cooler is controlled by HIC from control system , So if on Air cooler we will consider 2 individual I/P converter or positioner?
0 Answers Chagalesh Consulting Engineers,
How can we say that accuracy of measurement increases by using 3 or 4 wire RTD? because for example: If resistance of RTD element is say r ohms and Resistance of the cable from transmitter to RTD is R ohms And if 4 wire RTD is used, ____._____________________ R ohms | |_____._____________________ R ohms / \ / r ohms \ \ | |______.__________________ R Ohms | |_______._________________ R ohms Then the actual resistance measured will be: Total = r + R/2 + R/2 = r +R Ohms Note: r+R instead of r ohms. hence error
In field side transmitter voltage droping here no loose connection then what will happen?
What is the Difference between PE,IE and ISE
what is the electrical operation procedure for switching on 27.6MVA electric furnace.
Somebody tell me in what way i need to prepare for csio pgrpe(adv instrum eng)interview?what all the quest can i expect?
In power plant to measure vibration of a turbine we install sensors. Before install this sensor we have to set gap voltage. What is meant by gap voltage and its use?