How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper




Answers were Sorted based on User's Feedback



How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / sanoj

For calculating the productivity we have to know the
capacity of Excavator.

Let me assume the capacity of the Volvo 210 excavator =
1.22 Cum.

Consider the efficiency as 75% (This may be changing based
on the type of material to be excavated)

Therefore, net capacity = 1.22*75%= 0.92 Cum.

time per swing(unload,swing,fill,swing) = 20seconds =>
20/60 = 0.33minutes

Consider 5 minutes rest taken by the operatoer per hour.

Therefore, no of cycles per hour = 55/0.33 = 165

capacity per hour = 165*0.92 = 151.8 Cum/Hour

In similar fashion for dozer and other equipment can be
calculated.

Is This Answer Correct ?    110 Yes 33 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / m subbramanian

Along with above calculation, the distance travelled by the machine should also been taken into account.

Is This Answer Correct ?    44 Yes 5 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / manumitra singh

case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum

Is This Answer Correct ?    22 Yes 4 No




How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / ashebir

calculation for productivity of construction equipment

Is This Answer Correct ?    6 Yes 1 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / mickey

There is a program can calculate that based on type of soil, distance to dump site etc. MechaNorm by Giant Robot Systems

Is This Answer Correct ?    2 Yes 1 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / vinod k

I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.

Is This Answer Correct ?    0 Yes 1 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / mandar

i believe that the 75% efficiency taken is of operator then the rest taken is not applicable as it is included in the efficiency. As well the material swell factor and the bucket fill factor should also be taken in account plus the machine availability factor should be also accounted (generally less 85 to 95% considered).

Is This Answer Correct ?    1 Yes 6 No

Post New Answer



More Civil Engineering Interview Questions

Why is loose concrete removed from the surface where new concrete is to be done?

2 Answers   Ansals,


How to estabilish reinforcement Steel rolling margin for a building projects ?

0 Answers  


what are the duties of Site Engineer in work site?

0 Answers   Amarprakash Developers,


I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.

0 Answers  


Deshuttering time for slab 6.15 meter

2 Answers  






how to calcalate for roof beams & slab reinforcement design specified?

1 Answers  


what is the criteria for the finalisation of pavement thickness in road project?

1 Answers  


Prop carrying load capacity

1 Answers   NCCL,


How to calculate the material for pile 450 mm dia & 300 mm dia with formula find Cement = ? Sand = ? Blue metal = ?

1 Answers   Suda,


sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience

0 Answers   Rail Vikas Nigam Limited RVNL, RRB, L&T,


Can fly ash bricks can be used in brick bat coba?

1 Answers  


what is the m25 test result 7 days 14 days

3 Answers  






Categories
  • Civil Engineering Interview Questions Civil Engineering (4652)
  • Mechanical Engineering Interview Questions Mechanical Engineering (3710)
  • Electrical Engineering Interview Questions Electrical Engineering (15818)
  • Electronics Communications Interview Questions Electronics Communications (2685)
  • Chemical Engineering Interview Questions Chemical Engineering (763)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (127)
  • Bio Engineering Interview Questions Bio Engineering (30)
  • Metallurgy Interview Questions Metallurgy (95)
  • Industrial Engineering Interview Questions Industrial Engineering (199)
  • Instrumentation Interview Questions Instrumentation (2884)
  • Automobile Engineering Interview Questions Automobile Engineering (171)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (74)
  • Marine Engineering Interview Questions Marine Engineering (103)
  • Power Plant Engineering Interview Questions Power Plant Engineering (170)
  • Engineering AllOther Interview Questions Engineering AllOther (1371)