How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / sanoj

For calculating the productivity we have to know the
capacity of Excavator.

Let me assume the capacity of the Volvo 210 excavator =
1.22 Cum.

Consider the efficiency as 75% (This may be changing based
on the type of material to be excavated)

Therefore, net capacity = 1.22*75%= 0.92 Cum.

time per swing(unload,swing,fill,swing) = 20seconds =>
20/60 = 0.33minutes

Consider 5 minutes rest taken by the operatoer per hour.

Therefore, no of cycles per hour = 55/0.33 = 165

capacity per hour = 165*0.92 = 151.8 Cum/Hour

In similar fashion for dozer and other equipment can be
calculated.

Is This Answer Correct ?    104 Yes 32 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / m subbramanian

Along with above calculation, the distance travelled by the machine should also been taken into account.

Is This Answer Correct ?    40 Yes 5 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / manumitra singh

case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum

Is This Answer Correct ?    20 Yes 4 No




How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / ashebir

calculation for productivity of construction equipment

Is This Answer Correct ?    6 Yes 1 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / mickey

There is a program can calculate that based on type of soil, distance to dump site etc. MechaNorm by Giant Robot Systems

Is This Answer Correct ?    2 Yes 1 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / vinod k

I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.

Is This Answer Correct ?    0 Yes 1 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / mandar

i believe that the 75% efficiency taken is of operator then the rest taken is not applicable as it is included in the efficiency. As well the material swell factor and the bucket fill factor should also be taken in account plus the machine availability factor should be also accounted (generally less 85 to 95% considered).

Is This Answer Correct ?    1 Yes 5 No

Post New Answer



More Civil Engineering Interview Questions

fe415

7 Answers  


if column length is 12'(feet) then how to take ring bar on it?

2 Answers   AGI Infra, SIPL,


Terms Name the bars which is used in beam and colume ? Like starter bar etc.

1 Answers  


what happens when the curing is not done properly for structures ??

1 Answers   ANP,


HOW CAN DESIGN LENGTH,WIDTH AND HEIGHT THE FOUNDATION FOR THREE FLOOR BUILDING?

3 Answers  






what is construction joint? why do we give expancion joint in building?

4 Answers   L&T, jusco,


how much weighs a square feet of slab of 5 inches thick

2 Answers  


How much quantity of cement Bag for block masonry (1:4) for 1 cu.m? Block size (150x200x400) Mortar Thickness 20mm

0 Answers  


area of 8mm rod

5 Answers   INDUS,


Why chairs are provided at slab?

3 Answers   DLF, Kalpakkam, SKYi,


what is the permissible safe bearing capacity of soil?

7 Answers   Indian Railways,


estimate quanitity of bricks(19x9x9cm without mortar), cement & sand in 10feet X 10feet wall ?

0 Answers  






Categories
  • Civil Engineering Interview Questions Civil Engineering (4632)
  • Mechanical Engineering Interview Questions Mechanical Engineering (3698)
  • Electrical Engineering Interview Questions Electrical Engineering (15757)
  • Electronics Communications Interview Questions Electronics Communications (2635)
  • Chemical Engineering Interview Questions Chemical Engineering (761)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (79)
  • Bio Engineering Interview Questions Bio Engineering (30)
  • Metallurgy Interview Questions Metallurgy (95)
  • Industrial Engineering Interview Questions Industrial Engineering (199)
  • Instrumentation Interview Questions Instrumentation (2877)
  • Automobile Engineering Interview Questions Automobile Engineering (171)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (41)
  • Marine Engineering Interview Questions Marine Engineering (62)
  • Power Plant Engineering Interview Questions Power Plant Engineering (169)
  • Engineering AllOther Interview Questions Engineering AllOther (1334)