How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answers were Sorted based on User's Feedback
For calculating the productivity we have to know the
capacity of Excavator.
Let me assume the capacity of the Volvo 210 excavator =
1.22 Cum.
Consider the efficiency as 75% (This may be changing based
on the type of material to be excavated)
Therefore, net capacity = 1.22*75%= 0.92 Cum.
time per swing(unload,swing,fill,swing) = 20seconds =>
20/60 = 0.33minutes
Consider 5 minutes rest taken by the operatoer per hour.
Therefore, no of cycles per hour = 55/0.33 = 165
capacity per hour = 165*0.92 = 151.8 Cum/Hour
In similar fashion for dozer and other equipment can be
calculated.
| Is This Answer Correct ? | 139 Yes | 38 No |
Answer / m subbramanian
Along with above calculation, the distance travelled by the machine should also been taken into account.
| Is This Answer Correct ? | 44 Yes | 6 No |
Answer / manumitra singh
case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum
| Is This Answer Correct ? | 29 Yes | 5 No |
Answer / ashebir
calculation for productivity of construction equipment
| Is This Answer Correct ? | 8 Yes | 1 No |
Answer / mickey
There is a program can calculate that based on type of soil, distance to dump site etc. MechaNorm by Giant Robot Systems
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / vinod k
I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.
| Is This Answer Correct ? | 1 Yes | 2 No |
Answer / mandar
i believe that the 75% efficiency taken is of operator then the rest taken is not applicable as it is included in the efficiency. As well the material swell factor and the bucket fill factor should also be taken in account plus the machine availability factor should be also accounted (generally less 85 to 95% considered).
| Is This Answer Correct ? | 1 Yes | 6 No |
what is bulkage
which grade of concrete is the strongest? M20,M25,M30,M35 or M40?
What are the uses of layer?
Define Who designed the city of Washington DC?
what is PEB structure
What is alternate bid?
what is the procedure for flakiness and elongation index
how many types of survey and what are levelling instrument?
I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?
WHAT IS THE RATIO OF CEMENT:SAND:COARSE AGGREGADE IN M-20, M-25, M-30, M-35, M-40, M-45, M-50 CONCRETE?
Brick size ? & 1 square feet brick work for use brick
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)