Answer / Amrit Kumar Vashistha

To design a built-up column carrying an axial load of 1200 kN with a length of 8 m, you can use steel sections such as channels or angles. Here's an example solution using four equal CH250x100 channel sections:

Number of sections = Load / (Yield stress * Cross-sectional area per section)
Load/section = 1200 kN / 4 = 300 kN
Area per section = 250 mm x 100 mm x 1 = 25,000 mm^2 = 25,000 cm^2 = 0.025 m^2
Yield stress = 250 MPa = 250 N/mm^2

Axial load per section = 300 kN = 3,000,000 N
Yield force per section = 3,000,000 N / 250 N/mm^2 = 12,000 mm = 12 m (assuming no end fixity)

Therefore, the column length should be greater than 12 m to accommodate four equal sections with an overall length of 8 m.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

How you will differentiate in field between grade43 and grade53 catagory cement?

14 Answers   Gammon, NBN,


Laboratory experiments conducted in Mumbai on a particular mix showed a strength of 33 MP a for a fully matured concrete. Find whether formworm can be removed for an identical concrete placed at Jammu at the age of 15 days when the average temperature is 60C. The stripping stress in concrete

2 Answers   CCIL,


castigliano's theorems are based on

6 Answers   Essar,


what is the length of a steel bar when it buy for the site????

4 Answers  


What is mean by Rolling Margin Of Steel????

4 Answers   Dilip Buildcon, L&T, NCCL,


How do we calculate the power of centrifugal pump?

1 Answers  


How to convert n/mm2 in to kg/cm2?

38 Answers   Rvr Projects Pvt Ltd, Soma Enterprises, Unitech, Wipro,


koi bta sakta ha ka steel ko calculate krna ka full mathod pls

4 Answers  


the distrubution system in water supplies is designed on the basis of avg daily demand peak hourly demand coincident of draft greater of B & C

1 Answers  


What are wooden shingles?

1 Answers  


What are the alternate material for steel, Sand and aggregate

1 Answers   NASA, Simplex,


The ff slab casted its thickness 100mm.2nd floor slab will be casting its 300 mm.how we shall be given suppot to that 300mm thk slab.ple way me

3 Answers   Brigade,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)