Answer / satish`
yield stress of the steel for Fe 415 is 415 n/mm2 and for Fe
500 is 500n/mm2
Is This Answer Correct ? | 60 Yes | 12 No |
Answer / krishna prasad
yield stress of the steel for Fe 415 is 415 N/mm2 and for Fe
500 is 500N/mm2
Is This Answer Correct ? | 35 Yes | 4 No |
Answer / kumar
Question-
spouse u get below 1 meter cut bar, than how to define this is fe415 & fe500 steel bar.
Is This Answer Correct ? | 6 Yes | 1 No |
FE 415 has tensile strength 415 N/MM2 & FE 500 N/mm2 has
tensile strength 500 N/mm2.
Is This Answer Correct ? | 8 Yes | 6 No |
Answer / s p sharma
Q: What is the diffrence between FE 415 & FE 500 TMT BARS
Ans: 415 and 510 represent the 0.2% proof stess. There is
no well defined yield stress for HYSD Bars.
Is This Answer Correct ? | 7 Yes | 6 No |
Answer / dilip w,jadhao
The difference is only by strength i.e.FE 415 has 415 N/M^2
and for FE 500 strength has 500 N/M^2
Is This Answer Correct ? | 5 Yes | 4 No |
Answer / s p sharma
FE415 and FE500 have proof stress of 415 and 500 N/mm2 for
the residual strain of 0.2% as the above steel do not have
a well defined yield stress.
Is This Answer Correct ? | 5 Yes | 6 No |
13. What are your expectations from this possible relocation to our company?
What is the different type of slump test indications?
how to remove the quantity of metal 1 and metal 2 in concrete
Which pavement is advisable in India?(Flexible or Rigid)
Difference b/w tor steel or tmt bar
1) what do you mean by rolling margin of steel ? 2)pls. tell the cut length formula of stirrups as per IS codes(take out cut length for a beam of 600*300mm with 40mm cover all sides)? 3)what is the multiplying factor of painting for sand faced plaster? 4)if your footing is of size1.9*1.6m . what quantity of length and width you will excavate means what extra margins you will allow as per IS codes in billing?
How to calculate measurement box size for M25 grade cement?
3 Answers Perunding Omega PMC,
Can anybody tell me how to calculate the quantity of a trapezoidal footing?With its formula and an example.
I want to join bhel because
Let suppose A building wall is 12 ft high and 30 ft long and labour cost is 100 rupee per feet so calculate the total cost of labour and also explain in detail...plz ans me immadiately i am hurry Thanx
What is the ratio of Grades M10,M15,M20,M25,M30,M35,M40.
How much concrete can be made using one bag of cement?