Why two main buses and one transfer bus scheme not using
for 400kV switchyard

Answers were Sorted based on User's Feedback



Why two main buses and one transfer bus scheme not using for 400kV switchyard..

Answer / rishi

first of all who told u that main and transfer bus is not used in 400 kv substation.This scheme is used in many substations.

Is This Answer Correct ?    14 Yes 2 No

Why two main buses and one transfer bus scheme not using for 400kV switchyard..

Answer / naresh.devarakonda

one and half breaker scheme is more reliable, simple
operation and reduces the no. of isolators, bus.

Is This Answer Correct ?    4 Yes 2 No

Why two main buses and one transfer bus scheme not using for 400kV switchyard..

Answer / furqan ahmad

in one and halfbreker scheme scheme both breaker and bus
maintenance is possible.even though this scheme is costly
as compared to other schemes but becoz of reliability and
redundancy it is usually used for 400 kv switchyard

Is This Answer Correct ?    2 Yes 0 No

Why two main buses and one transfer bus scheme not using for 400kV switchyard..

Answer / jkrocks

DMT scheme is used earlier in 400kV System but all new 400kv ss are made on one & half breaker scheme. it has many advantages over DMT scheme.
more reliable than DMT each time line or ICT remain connected through both buses I & II, reduces numbers of confusing isolator in system, reduce additional bus.
If one bus trip due to any fault , lines are transformer connected to that bus remains charged through another bus by means of Tie CB.

Only disadvantage is that this system require three breaker for 2 lines or transformer.
But It is nothing against lots of advantages of One & Half Breaker Scheme.

Is This Answer Correct ?    2 Yes 0 No

Why two main buses and one transfer bus scheme not using for 400kV switchyard..

Answer / teju

one and half circuit breaker scheme is more reliable than
other schemes, simple operation and reduces the no. of
isolators, some electrical parameters & it is easy to handle.

Is This Answer Correct ?    0 Yes 4 No

Post New Answer

More Electrical Engineering Interview Questions

3 ph motor connected in star delta starter. when we start the motor it run in star but when in is going in delta it trips the main incoming supply. why?

3 Answers   Bajaj Hindusthan,


howmany insolaters needed in 66kv line

9 Answers   Essar, L&T,


we can conformed the vector group of the transformer. How?

0 Answers  


whati s the sludge current in ups

0 Answers   Future Group,


what is reactive power?

8 Answers  






how and why are capacitors are used to improve powerfactor?

4 Answers  


How to confirm the Phase shifting Transformer VECTOR GROUP relation , as below ZNy11.45d10.45-ZNYy0.15d11.15

0 Answers  


What's the differs between voltage & current & emf.

1 Answers   CTS, NTPC, TCS,


3phase motor 400v (induction) A.C 4kw company design 1400rpm but our requirement 2000rpm possible? attached any instrument. reply fast! contact 03343262442

3 Answers  


Can you explain about pole discrepancy scheme

0 Answers   NCC,


Pls tell me what is the exact current conducting capacity of copper and aluminium cables?how much capacity of cables need to 90kw induction motor&how?

1 Answers  


How to calculate KW what is the formula for KW.

18 Answers   Toyota, UU,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)