For a 50MVA (138/69/13.8 KV) transformer, what would be the
maximum demand in order not to exceed 80% of its operating
capacity.

Answers were Sorted based on User's Feedback



For a 50MVA (138/69/13.8 KV) transformer, what would be the maximum demand in order not to exceed ..

Answer / m.premkumar

We cannot decide straight away to 80 %,It depends on what
is our Load, i agree we can go upto 80% of transformer
capacity, Say 40 MVA.I had the experiance we did wrong
calculation and we got 1500 KVA as MD but we are using only
200 KVA,so unnecessarily we are paying money to the
Electricity board.

Is This Answer Correct ?    1 Yes 0 No

For a 50MVA (138/69/13.8 KV) transformer, what would be the maximum demand in order not to exceed ..

Answer / k.prakashchandra

Max demand is in MVA and hence 40 MVA

Is This Answer Correct ?    0 Yes 2 No

Post New Answer

More Electrical Engineering Interview Questions

How many speed of dg start motor for engine starting time

1 Answers  


What is type of transformers?

3 Answers  


Hi My Dear All Friends, There is one question it is widely used in Power Project's High Voltage Engineering. Question- What is the diffrence between Earth fault and Back up Earth Fault....???? . . . . . . Have A Good Day

1 Answers  


what is Ith current?

4 Answers  


how to find insulation resistance of a generator(11kv) by theoritical formula??

1 Answers  






Is it weather conditions make any problems to the electrical equipments and if yes means is it any precautions needed?

1 Answers   Hexaware,


what ll happen if neutral is not shorted with phases while doing transformer short circuit test & what ll happen if neutral is connected to ground?

1 Answers  


a transformer can beb used as aload?give discription

2 Answers   Esses Eltech Systems,


what is differance bw ELCB and MCB. ?

3 Answers  


what is diffrence between dc motor and dc generator?

3 Answers   HBL Power Systems,


What do you mean by a current transformer?

0 Answers  


We have three 33kv substations. All of them energised by same source.When i am checking the phase sequence between one substation to other substation (like R Phase to R Phase) by multimeter i am getting some voltage.Near to LT panels UPS panels are there. Can u explain whether any possible to happen like that. In Phase SEquencemeter is showing correctly in both substations. How is it happen. Explain me.Explain me communication signal will produce Phase difference on this case.

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)