what is the difference between rise and tread? what is its
standered size? what is waist slab?what is the standered
length of staire-case? also what is the angle between floor
and landing?
Answers were Sorted based on User's Feedback
Here in the staire case RISE or RISER means short vertical
portion of the step and TREAD means the short horizintal
portion where we put or feet. The standards of the RISE
is 15 cm or 6" and that of TREAD is 30 cm or 12". Waist
slab means the supporting slab for all the steps which is
usually 10 cm (4") to 15 cm (6") thickness. And lastly
the angle between the floor and the landing should be 22.5
degrees to get the standard size of the steps otherwide we
have to increase or decrease the riser or tread.
| Is This Answer Correct ? | 24 Yes | 0 No |
Answer / sivasubramanian
Tread is horizontal Portion and Riser is vertical portion.
Tread 10-12 inch & Riser 6-8 inch.
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / prabu
tread = 250 - 300 mm
rise = 150 - 200 mm
staircase width = 0.85 - 1.5m
span/depth = 20
depth of stair case slab minimum= 160 mm
angle of staircase= 30 -45 degree
live load on staircase = (5kn/m2 max)
| Is This Answer Correct ? | 1 Yes | 2 No |
Answer / sjtbehera
tread means where you landing your feet. rest is called rise
standar size is tread=9" and rise = 6"
Waist slab is the platform whsre slab is turned
standar length os stair case is - 6"x15"
last qouestion i donot understand
| Is This Answer Correct ? | 2 Yes | 11 No |
Answer / suman biswas
tread is the horizontal portion of a step,on which we place our feet
rise is the vertical portion of step supporting the tread
standard size :16cm(rise)*26cm(tread)
the length of stair-case may differ,but the no of steps should not be less than 3 and more than 12 for one flight...
the angle between floor and landing is 30-45 degree
| Is This Answer Correct ? | 0 Yes | 9 No |
how you can say about a slab that it is one way or two way.
grade of cement used for plastering? why?
4 Answers Green Valley Shelters (P) Ltd, NCCL,
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
what is tensile strength?
what is the difference between red bricks& cement bricks
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton
how to convert kg/m3 to kg/cft
plz tell me one brick total plaster area?
9 Answers Aparna Constructions, Aparna Enterprises, L&T,
how calculate the ms angle weight formula detail
9 Answers Concor, Puravankara,
convert 1 kilo into brass
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)