How do you derive the quantity of cement & sand in brick work
construction in 1Meter cube, using CM 1:6 and bricks of size
19*9*9 cm
Answers were Sorted based on User's Feedback
Answer / sag
Volume of bricks with mortar=.2*.1*.1=.002
No of bricks=1/.002=500
Volm of 500 bricks=.19*.1*.1=.7695
Volume of mortar=1-.7695=.2305
Add 15% for wastage and 30% for dry mortar
Now volume of plaster=.2305+.2305*.15+.2305*.3=.334
1:6 cement and sand 1+6=7
Volume of cement=1/7*.334=.048m3=1.36 beg
Volume of sand= .048*6=.288m3
| Is This Answer Correct ? | 33 Yes | 5 No |
Answer / mandeep thakur
By this Formula we can Work out roughly, But Not 100%
Correct
0.3*28.8/sum of Ratio e.g(1:4 is equal 1+4=5
than .3*28.8/5 Only For brick Work.
| Is This Answer Correct ? | 9 Yes | 5 No |
Answer / prakash
3/1+6=0.42 cum cement and 2.57cum sand required ,brick for 1
cm is 500 nos
| Is This Answer Correct ? | 2 Yes | 3 No |
Answer / saif raza
1# Brick required :- 650 nos
2# Cement :- 1.23 bags
3# Sand :- 0.25 cum
| Is This Answer Correct ? | 4 Yes | 8 No |
.want to know the volume of water for 1.2.4 concert mixing ratio
what is the allowable silt content in concrete?
about higyway engineering
What is made from large rocks, which protects the base of cliffs?
What Should be the CBR Value for Transported (Selected) Soil.whether it can be 5% or not ?
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
6mm dia rod legth 1feet
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
why grading of cement is like 33,43,53?why not 25,35,45?
1 Answers Gokaraju Rangaraju Institute of Engineering and Technology GRIET,
I had a plot of say 5000 sq.ft. and soil in the plot is normal soil. Now I had to work upon the tender quantities to prepare a preliminary budget within a day. Is there any thumb rule or assumptions to calculate the quantities which can differ upto 15% +/-?
how to know rcc strength
how many cement in cubic feet of 40 kg bag white cement.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)