I had a plot of say 5000 sq.ft. and soil in the plot is
normal soil. Now I had to work upon the tender quantities
to prepare a preliminary budget within a day. Is there any
thumb rule or assumptions to calculate the quantities which
can differ upto 15% +/-?
Answers were Sorted based on User's Feedback
Answer / pravinkumar borling
to calculate for preliminary budget,it can calucated by
multiplying built-up area into rate per sq.ft as per
today's market rate it cambe taken rs.1200 per sq.ft
Is This Answer Correct ? | 8 Yes | 0 No |
Answer / n.c.pathan.
Estimation can be done in a day. It will require a plan.
However if you are interested in the cost of the structure
it will cost you approximately Rs.1250 per square feet with
normal specifications.
Is This Answer Correct ? | 7 Yes | 4 No |
how much repeitation for conventional and maivan formwork?
what is 3.14 indicates for cutting length of stirrups
in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?
What is oneside mat. And explain
how to convert sand in Cft to Kgs
what will be the quantity of following materials in P.C.C for the total area of (100'x70'x 0'4") 1)NO. OF CEMENT BAGS 2)SAND IN CU.FT 3)METTLE IN CU.FT
0 Answers Pratibha Industries,
how to calculate circular slab reinforcement (6m dia 0.15mmthick)
what is design life of steel structures??
how many liters of water required for 1cu.m concrete?
how to calculate cutting length in bar bending schedule for 180 degree bend? for 90 degree bend we take 2d i.e we -2d for 180 degree ho much ? question asked at l&t
what is the maximum percentage of crush sand in mix design.also what is the difference betweeen grite powder & crush sand.
2 Answers TATA, Vastu Kirti Enterprises,
how much minimum steel provide in column