How do you derive the quantity of cement & sand in brick work
construction in 1Meter cube, using CM 1:6 and bricks of size
19*9*9 cm
Answer Posted / sag
Volume of bricks with mortar=.2*.1*.1=.002
No of bricks=1/.002=500
Volm of 500 bricks=.19*.1*.1=.7695
Volume of mortar=1-.7695=.2305
Add 15% for wastage and 30% for dry mortar
Now volume of plaster=.2305+.2305*.15+.2305*.3=.334
1:6 cement and sand 1+6=7
Volume of cement=1/7*.334=.048m3=1.36 beg
Volume of sand= .048*6=.288m3
| Is This Answer Correct ? | 33 Yes | 5 No |
Post New Answer View All Answers
whaat is blister in box girder bridge and what is its function..
how to calculate spacing rod in column
How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction
Explain what is structural frames or systems?
What are the uses of groynes?
how to convert cement, sand aggregate quantity from M3 to kg with full description?
The portion of a brick cut across the width is called?
crank types
Slump Values for works?
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
rate analysis for cement pointing 1:4 , for 100 sq m
what is density of 20mm coarse aggregate.plz send answer my below adress e.mail
How foundation is designed, Column design and beam design
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
Are cruise ships built for the transatlantic run?