Answer / mahendra mohan srivastava
first we can weight sample of sand then we can take it to
SSd condition then we calculate moisture and if moisture is
6 % then bulkage will 30 % so we can put 6% less water and
30% execss sand after correction.if moisture will exess to
6 % then we will take less water equal to moisture and sand
will not exceed.
| Is This Answer Correct ? | 29 Yes | 18 No |
Answer / rojas james
Bulkage of sand is used to determine the change in volume of sand when doing volume batching, when moisture is there in sand upto a limit the volume will increase then after saturation the volume will decrease so in volume batching if sand is having moisture the volume will be shown high than the actual and it can make the mix to segregation due to less Fine Aggregates
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / suresh
this is not answer.
my question ... first we check and give moisture correction.
this is ok. in that same time why we have required of
bulkage of sand..?
bulkage of sand: we have using only volumetric based place
not in weighement location.
| Is This Answer Correct ? | 7 Yes | 6 No |
Answer / sai
By proctor test we can find dry density,and water content by any mtd like cal. Carbide then by using formula we can find bulk density
| Is This Answer Correct ? | 0 Yes | 0 No |
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
What is mix design
What is the benefit of making a cantiliver proped.?
7 Answers CCCL, Engineers India Limited,
what is meant by workebility of concrete?i have studied about it much but i can't clear about it.so plz give me a detail explanation in simple english or urdu ?
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
Hi Dudes, I have completed B.E Civil with two years experience in Highway& Bridges. One year experience in Site field & One year experience in Planning & Billing Dept. I am willing to work in abroad, i am having passport and all..So if anybody knows about foreign vacancy pls inform me..Ph:9994050979 & Mail Id: Simacivil1988@gmail.com
clean earthing and dirty earthing
1 Answers CSCEC-China State Construction Engineering Corporation,
All aptitude question of Bechtel
if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel
castigliano's theorems are based on
what is quick sand
For a RCC section with congested reinforcement , what is the compaction factor
3 Answers Arihant, GMR, Gulf International Contracting, NBCC,
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)