How to check percentage of bulkage of sand in RCC?
Answer Posted / suresh
this is not answer.
my question ... first we check and give moisture correction.
this is ok. in that same time why we have required of
bulkage of sand..?
bulkage of sand: we have using only volumetric based place
not in weighement location.
| Is This Answer Correct ? | 7 Yes | 6 No |
Post New Answer View All Answers
In earth work 1300 cum soil how to calculate how many liters require in water
why building got air crack? if it get in one particular are what is means?
Which code is used for tor & tmt steel bar?
if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
very simple or less time consuming formula for reinforcement calculation by moment
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)
how many types of survey and what are levelling instrument?
what are the types of dimensioning?
what is the tensile strength of 10swg and 8swg gabion wire?
What is the cost difference between site mix and ready mix concrete per cubic meter
a butt weld is specified by
What is GSB gradation
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation