How to check percentage of bulkage of sand in RCC?
Answer Posted / mahendra mohan srivastava
first we can weight sample of sand then we can take it to
SSd condition then we calculate moisture and if moisture is
6 % then bulkage will 30 % so we can put 6% less water and
30% execss sand after correction.if moisture will exess to
6 % then we will take less water equal to moisture and sand
will not exceed.
| Is This Answer Correct ? | 29 Yes | 18 No |
Post New Answer View All Answers
What is Density of cement, sand & aggregate ?
Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
what is the 0 value in quantity surveying
i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............
I need to constructive work in amaraj batteries
What is the strength of 1:6:12 mix?
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
can i get civil engineering test papers.......?????
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
pls mail some more tecnical qustions at msaranya2610@gmail.com
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?