What is the correct procedure to shutdown VCB in 11kv
substation.safety and work procedure
Answers were Sorted based on User's Feedback
Answer / balaji
1. Preparation (Permit to work)
2. Separation (Trip the Breaker)
3. Isolation (Isolator isolates)
4. Earthing & Short circuit (Earthing)
5. Screening & Marking the area (Barricading the work area)
| Is This Answer Correct ? | 11 Yes | 2 No |
Answer / manzoor hussain
1)First need to obtain isolation permit(work permit)
2)Confirm substation no., breaker no.
3)Inform to control engineer
4)Transfer the load from LV side
5)First need to trip the vcb(electrically or manually)
6)Disconnect DS switch (isolator)
7)Need to close the earth switch (ES)
| Is This Answer Correct ? | 0 Yes | 0 No |
Hello friends i am facing one problem in lighting panel. Frequently neutral link near to MCCB is burning(firing. What may be the reason for this one. Please answer me.
WHY IS THE SIZE OF HOLE OF THE EARTH POINT IN THE PLUG POINT BIGGER THAN PHASE AND NEUTRAL
bit confused - am i correct in thinking that to determine line to line voltage in a star config 110v 3 phase 4 wire distribution system i would use a voltmeter? I have a circuit configured as an unbalanced load, consisting of three incandescent lamps (1x40w, 1x60w, 1x100w - all 110v rated)connected in a star configuration to a 110v 3 phase 4 wire distribution system. I want to find out what types of meters i would use to obtain: a) each line to line voltage b) the line to neutral voltage across each load c) current flowing in each line and load d) current flowing in the neutral conductor e) power supplied to the loads im assuming i would be using ammeters in series along each line and voltmeters in parallel across each line to neutral? Also how could i predict these meter readings before taking them and with which formulae? Any help would be greatly appreciated A.
Which type of alternator used in power station?
why corona loss is less with negative polarity?
what is meant by directional earth fault and non directional earth fault? describe both.
why do we have spikes enough to burn electronic boards, when generators are not grounded
a 11 kv line is grounded and a 110 kv line is grounded. which line have the greater current flow?
How much ampere rating on LT side of distribution transformer and also on HT side of 200KVA transformer
why the power cut problems occur in tamil nadu? may i know the exact reason.plz
explain why the secondary terminal of current transformer should not be lift open circuited.
can u give me a brief idea about power line carrier communication ??
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)