What is the correct procedure to shutdown VCB in 11kv
substation.safety and work procedure
Answer Posted / manzoor hussain
1)First need to obtain isolation permit(work permit)
2)Confirm substation no., breaker no.
3)Inform to control engineer
4)Transfer the load from LV side
5)First need to trip the vcb(electrically or manually)
6)Disconnect DS switch (isolator)
7)Need to close the earth switch (ES)
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How can ou verify the size of conductor 50Sq.mm ACSR
What is boucholz relay and the significance of it in to the trformer?
What is Load sharing of Transformer ?
what is proper capacitor placement? How to evaluate capacitor size?
What is the difference between multimeter
what are the assumptions made in swineburne's test?
How can find thermal state value in relay for calculate thermal overload.
What are the specifications for getting approval of Substation?
can u please mail me the syllabus for GET exam for damodar valley corporation?
Which power will flow first if we switch on a motor Active or Reactive? How?
defination of transistor controlled series capacitor
where does 22kv line starts
For group 1 , 2 whather i have to prepare my technical or general studies etc? and im graduate in ee engg. for wht posts im eligible for? please tell me!
which type of stability limit is higher,steady state or transient? why?
what kn of disc is used in 33kv,132kv,220kv,400kv,800kv transmission line