What is the correct procedure to shutdown VCB in 11kv
substation.safety and work procedure
Answer Posted / manzoor hussain
1)First need to obtain isolation permit(work permit)
2)Confirm substation no., breaker no.
3)Inform to control engineer
4)Transfer the load from LV side
5)First need to trip the vcb(electrically or manually)
6)Disconnect DS switch (isolator)
7)Need to close the earth switch (ES)
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
IF DISTANCE IS 100METERS B/W AMP.METER AND CURRENT TRANSFORMER WHAT WILL BE AFFECT IN ACCURACY .METER CAN SHOWING ACCURATE CURRENT OR NOT IF NOT WHAT CAN I DO TO GET 100% ACCURACY.
hello if any one have papers vof hpcl or sail, plz send me
What is the formula to calculate a three phase alternator
how to select electronic timer(Star-Delta) setting for diff. rating motors
why do we use 25kv supply for traction purpose?
can anybody sent me power grid questions. what subject should i prefer for preparation?
what causes contact chatter when there is no demand on the air conditioning unit?
why it is not advisable to run low rating (19KVA) DG sets in parallel for long durations even though they are provided with droop ckts (QDC)
What is the role of feedback in a closed loop control system?
What are the site acceptance tests for power cables, DG Sets, LT panels & 30kVA UPS ?
Why mostly the HV side of transformer has Delta?
how hydrogen cooled alternator undergo maintanence ? that is hydrogen when come in contact with air can result into explosions .
1.why we are using metal oxide gapless block in lightning arrester,2.What is minimum and maximum rating of metal oxide blocks using in india
How harmonic block test are conducted on relays ( Siemens,Areva ect )power transformer using omicron kit?
in india per day how much power is generated including all power station