Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Answers were Sorted based on User's Feedback
Answer / pravat
Volume=π/4 {Ld^2+0.4N(D^2-d^2)(D-d)}
Where d=dia of pile
D=dia of under ream
L=length of pile
N= no of under ream.
This the formula for pile with any no of under reams.
Is This Answer Correct ? | 52 Yes | 13 No |
Answer / h kumat
Volume of pile = A
= 3.14×(0.30/2)²×10=0.707m³
Volume of two undeream = B
=2× 2.44(0.30)³=0.13 m³
Totol volume of pile & underream=A+B
=0.707+0.13= 0.837m³
Be sure about shape of underream before use this formula.
Is This Answer Correct ? | 23 Yes | 15 No |
Answer / amit kumar sachin
Rcc Volume of 2no. Bulb (without pile rcc)
Formula = π/4 {0.4N(D^2-d^2)(D-d)}
Where d=dia of pile
D=dia of under ream(bulb)
N= no of under ream.
Calculation-
Dia of bulb(D)= 2.5 times of dia of pile
D=2.5×0.30 =0.75m
Rcc volume= π/4 {0.4×2×{(.75)^2-(.30)^2}(.75-.30)
= 0.133 m^3
Is This Answer Correct ? | 8 Yes | 2 No |
Answer / dr. maninder singh khalistani
Volume of underream=2*3.14*.3*.3*.3/6=. 028m3
Is This Answer Correct ? | 2 Yes | 3 No |
Answer / saideepak nagajjanavar
Pile length- 10 m
Pile dia- .15m
10X.15X.15=0.225
0.225X3.142=0.7069
Ans:07069
Is This Answer Correct ? | 5 Yes | 7 No |
Answer / aman kumar
Length of bulb=0.55 m
Dia. of bulb=2.5*0.3=0.75 m
Extra for bulb=0.75-0.3=0.45 m
Bulb volume= Area*Perimeter=1/2*0.55*0.225*3.14*0.3=0.058 cum for 1 bulb.
Pile volume=3.14/4*0.3*0.3*10=0.707 cum
So, For 1 bulb,Total quantity=0.707+0.058=0.765 cum
And For 2 bulb,Total quantity=0.707+2*0.058=0.823 cum
Is This Answer Correct ? | 4 Yes | 8 No |
Answer / lisy rajan
Quantity of concrete= 2* 3.14*.15*.15*10=1.413m3
(with out deducting steel)
Is This Answer Correct ? | 4 Yes | 12 No |
Answer / bharath m,+91 8438238335/99806
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Solution :
(Pls. refer construction practice book & IS 2911 Part-III.)
2 under reamed pile means there are 2 Nos. of bulbs at particular spacing based on friction of soil.
Dia. of pile : 0.30 m. ie.,bulb dia. = 2.5 times dia. of pile
So it is 2.5*.3 = .75 m.
Length of Pile = 10.00 m.
Bulb thickness at pile intersection end (30-45degree inclination)= 1.75 times pile dia.
=1.75*.3
=0.525 m. &
free end = dia. of pile/4
=.3/4
=0.075 m.
Now follow the calculation:
Step 1:
Pile volume = Area x length
3.14/4*dxd x length
=3.14/4*.3*.3*10 = 0.707 Cubic Metre. ------1
Extra for Bulb Volume = Perimeter x Depth of bulb
=2*3.14*r x db
r at centre line of bulb = ((.75-.3)/2)+.3 = 0.525 m.
V=2*3.14x .525x(.525+.075)/2
=0.989 Cum. for 1 Bulb
V for 2 Bulb = .989*2
=1.978 Cubic metre -----2
Now combined Total Volume of Concrete 1+2 = .707+1.978 = 2.685 Cubic Metre.
Is This Answer Correct ? | 44 Yes | 52 No |
Answer / sai
steel should be subtracted from 7065 let it be 1 percent 7065-70.65=6994.35
Is This Answer Correct ? | 2 Yes | 12 No |
The largest size of paper used in plotter to print the drawing made by Autocad .
Define What is made from large rocks, which protects the base of cliffs?
how statics is different from dynamics
What is the percentage of wastage in steel reinforcement n how to control it?
sir, how to calculate steel per 1 m2
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
I heard Thump rule about beam depth is 1" per 1' length. Is this correct? If not please tell me the thump rule.Thanks.
How to fix steel in rectangular footins? I.e first along the length or first along the width??
What is the difference between stress and strength?
2nd and 4rt angle elevation used in which country ?
Permissible wastage of cement as per IS code ? In which IS code I get it?
How to plan a project
0 Answers Ahluwalia Contracts, SDS,