what is the real de-shuttering time for rcc column,slaband
wall
Answers were Sorted based on User's Feedback
Answer / shishir bhansali
rcc column 12 hours
rcc slab depending upon the span. from 5 days to 14 days
rcc wall 12 hours
Is This Answer Correct ? | 29 Yes | 3 No |
Answer / ravi kant sharma
Minimum 16 to 18hr for column for any grade of r.c.c.
Is This Answer Correct ? | 8 Yes | 0 No |
Answer / royalcivil
the de-shuttering time for the slab is 21 days must.
for the column it should be minimum of 1 week
Is This Answer Correct ? | 10 Yes | 26 No |
sir i have 2700sq.ft area.i wish to make a coomercial space including this area.sir what could be the estimated cost of 3 story bulding in varanasi.
What is the soil bearing capacity ? And how it should be to built a multistory building ?
3 Answers Clancy Networks, eConstruct, UltraTech,
where are using of one way slab ?
How may kgs. of sand make one brass ?
what is Tsunami. explain it's formation.
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
how to calculate the cutting length of steel? by which formula?
3 Answers MS Khurana Engineering,
how to calculate the quantity of bricks
The largest size of paper used in plotter to print the drawing made by Autocad .
How to find arc area with using angle?with out using angle?
How to ascertain the required grade of Steel is good for Site .....
how to start basic designing in structure..procedure to knw basic start to do structural designs in civil field?