what is the real de-shuttering time for rcc column,slaband
wall
Answers were Sorted based on User's Feedback
Answer / shishir bhansali
rcc column 12 hours
rcc slab depending upon the span. from 5 days to 14 days
rcc wall 12 hours
| Is This Answer Correct ? | 29 Yes | 3 No |
Answer / ravi kant sharma
Minimum 16 to 18hr for column for any grade of r.c.c.
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / royalcivil
the de-shuttering time for the slab is 21 days must.
for the column it should be minimum of 1 week
| Is This Answer Correct ? | 10 Yes | 26 No |
what is plate load test and what is the procedure of it and what is accessories which in use
why in india readymade structure is impossible in residence houses?
What is a hatch patterns?
Why we select pile foundations
how many hacking to be made in one sqft for concrete surface before plastering as per the IS Code
What is the per cu. mt. price of ready mix in Gujarat region.?
how much quantity a carpenter do shuttering per day
19 Answers Nexus Technologies, Tata Projects,
For fine aggregate which is most suitable River sand or crusher sand & why ?
The effect of arching the beam is?
What is modular elasticity?
what is the grade of 1:2:1 concrete mix
I have completed building maintenance course in mcvc stream .. can I apply for the post of " sthapstya abhiyantriki sahayyak"?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)