Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Answer Posted / amit kumar sachin
Rcc Volume of 2no. Bulb (without pile rcc)
Formula = π/4 {0.4N(D^2-d^2)(D-d)}
Where d=dia of pile
D=dia of under ream(bulb)
N= no of under ream.
Calculation-
Dia of bulb(D)= 2.5 times of dia of pile
D=2.5×0.30 =0.75m
Rcc volume= π/4 {0.4×2×{(.75)^2-(.30)^2}(.75-.30)
= 0.133 m^3
Is This Answer Correct ? | 8 Yes | 2 No |
Post New Answer View All Answers
what is thumb rule for calculating the size of ISMB required for a particular length of span
please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering
how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6
what are the types of design? which type of method is used at what type of design & why?
what isload waring calculation
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?
What is soil enforcement?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?
how to calculate quantity of bricks in circular manhole with examples.
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
IS code for grade of concrete for bamboo lintel????
what is civil engineer greatest strength and weakness?
How to identify the vitrified tile and ceramic tile by observation only after executing the job.
When was the first motorway built in england?