Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Answer Posted / aman kumar
Length of bulb=0.55 m
Dia. of bulb=2.5*0.3=0.75 m
Extra for bulb=0.75-0.3=0.45 m
Bulb volume= Area*Perimeter=1/2*0.55*0.225*3.14*0.3=0.058 cum for 1 bulb.
Pile volume=3.14/4*0.3*0.3*10=0.707 cum
So, For 1 bulb,Total quantity=0.707+0.058=0.765 cum
And For 2 bulb,Total quantity=0.707+2*0.058=0.823 cum
Is This Answer Correct ? | 4 Yes | 8 No |
Post New Answer View All Answers
Which are the Steel tests ?
can i get civil engineering test papers.......?????
what does the grad of cement shows (denotes)?
Civil engineering related
suppose that 156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.
Is there the dry coefficient of cement is constant?
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
What are the basic use of runners and standards of pipelines?
dialation means
what is the formula to find the diagonal shape stirrups?
what is the criteria for the finalisation of pavement thickness in road project?
How do you change a dimension value in solidsworks?
Define What is passive earth pressure ?
How many lbs are there in a yard?
Why joints are provided?