what is the main purpose of line PT and bus PT?..

Answer / nageswara rao

line pt means measure incoming line voltage and protect line
under voltage protection 88% of voltage,bus pt means measure
out going bus voltage and protect bus under voltage
protection for motor feeders,44% with time delay 3-5 sec,
pt means the potential transformer, which is used as a
instrument transformer in measuring device. its main use is
to step down the voltage at measurment levels.

Is This Answer Correct ?    115 Yes 15 No

what is the main purpose of line PT and bus PT?..

Answer / logachandran m

We are using Both Line& Bus PT(Potential Transformer) But different application.
1. Line PT- This PT using on main Incomers to Bus bar system or Main out going from Bus system,it will protect the particular feeder system. Ex,Transformer incomers,Generator incomer,etc,....
2. Bus PT- This PT using on Particular Bus bar system, It will protect the Bus Bar. Its will useful for Bus bar to bus bar synchronization or Bus bar to any source(Using with line PT)

Is This Answer Correct ?    39 Yes 8 No

what is the main purpose of line PT and bus PT?..

Answer / v.doraiswamy

Line PT:The Line PT is located on line side of the Feeder.
This will have normally has two secondary cores.The core
with accuracy cl.1 is used for metering purpose(ie)
measuring Voltage,watt,var etc. Core with accuracy cl.3P is
used for Porotection like distance scheme relay,
directional O/C,E/F relay. Also metering secodary core is
used synchronising the line with Bus.

Bus PT : The Bus PT functions are same as Line PT. But This
is located on the main Bus and this can be used for all the
circuits being located in the Bus. For cost point of view
it better to have common Bus pt for all the circuits.

Is This Answer Correct ?    13 Yes 4 No

what is the main purpose of line PT and bus PT?..

Answer / k.prakashchandra

In SS bus PT is used for metering and protection.For line
generally CVT is employed for PLCC and "live line" indication

Is This Answer Correct ?    9 Yes 7 No

what is the main purpose of line PT and bus PT?..

Answer / pardeep bathinda

1 Bus pt use for under / over voltage protection and measure for volt and synchronization time use for voltage matching
2 line pt use for income line voltage and protection line under and over voltage

Is This Answer Correct ?    3 Yes 1 No

what is the main purpose of line PT and bus PT?..

Answer / satale kiran

pt means the potential transformer, which is used as a
instrument transformer in measuring device. its main use is
to step down the voltage at measurment levels.

Is This Answer Correct ?    34 Yes 34 No

what is the main purpose of line PT and bus PT?..

Answer / ramji

Line PT has metering and Protection Cores. Its main use is
to mointor the Line Voltage parameters and is widely used
in protecting Lines in case of Faults occuring due to Phase
to phase faults and phase to earth faults which comes under
its review.

sometimes it has a core for meeting synch with respect
others incase the line breaker opens

Bus pt has metering core and protection core for BUS BAR
protn which mointors the faults in all the buses with
respect to that in a particular substation only

Is This Answer Correct ?    7 Yes 11 No

what is the main purpose of line PT and bus PT?..

Answer / vels

the sensitivity of voltage drop of line PT during the line
fault condition is high than a bus PT

vels

Is This Answer Correct ?    10 Yes 17 No

what is the main purpose of line PT and bus PT?..

Answer / mrudang

pt is use for metering and protection purpose
line PT is a government line
and bus pt is customer pt
we have to synchronise that both
generally pt protect the line with undervoltage ,
overvolateg protection

Is This Answer Correct ?    5 Yes 30 No

Post New Answer



More Electrical Engineering Interview Questions

PLC Training in chennai | PLC Training institute in chennai, PLC Training center in chennai | Best PLC Training in chennai | PLC Training course in chennai | SCADA Training in chennai | PLC Training in india

1 Answers   Exide,


What is meant by reverse polarity and how it can be fixed?

0 Answers  


how many number of terminals are available in CURRENT TRANSFORMER

6 Answers   MSETCL Maharashtra State Electricity Transmission Co Ltd,


It is desired to flood light the front of a building 42 meters wide and 16 meters hig.Projectors of 30 degree beam spread and 1000 watt lamps giving 20 lumen/watt are availabl.If the desired level of illumination is 75 lumen/m and show a suitable scheme.Assume the cofficient of utilization, deprecitation factor and waste light factor are 0.4, 13 and 1.2 respectively.

0 Answers  


why do we use spark detector inside the slip ring brush compartment 0ona slip ring induction motor?

0 Answers  






Can any one explain me about 2 phase motors ?

2 Answers   L&T,


why anti pumping relay is not given to tripping coil of the breaker? why only to closing coil?

2 Answers   INEL, Siemens,


In a synchronous machine if the field axis is ahead of the armature field axis then the machine is ?

1 Answers  


with out colour codeing on conductor how can be find what is r,what is b,what is y phases.....

0 Answers   Divis Laboratories,


Can the output voltage of a rectifier be greater than the input AC voltage without the use of any voltage multiplier in the circuit??please provide the explanation too..

0 Answers   IOCL,


What iz main protection of mediuum voltage motors and what iz the standard IR voltage of 6.6 and 11kv motors.

1 Answers   GE,


30 kVA and voltage 380/220VAC how to find out kA?

5 Answers  






Categories
  • Civil Engineering Interview Questions Civil Engineering (5076)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4445)
  • Electrical Engineering Interview Questions Electrical Engineering (16606)
  • Electronics Communications Interview Questions Electronics Communications (3915)
  • Chemical Engineering Interview Questions Chemical Engineering (1092)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (214)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (258)
  • Instrumentation Interview Questions Instrumentation (2992)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (123)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (0)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1378)