what is the main purpose of line PT and bus PT?
Answer Posted / nageswara rao
line pt means measure incoming line voltage and protect line
under voltage protection 88% of voltage,bus pt means measure
out going bus voltage and protect bus under voltage
protection for motor feeders,44% with time delay 3-5 sec,
pt means the potential transformer, which is used as a
instrument transformer in measuring device. its main use is
to step down the voltage at measurment levels.
| Is This Answer Correct ? | 129 Yes | 15 No |
Post New Answer View All Answers
wheather the size of windings in motor and generator are the same
what is differant beetween overload current and phase current?
what is the use of vcb & isolator in substation?
why we are not giving the zone 1 trip command to the master trip relay
how to design the heater in temperature control unit to heat 50KL of water?
What are the advantages and disadvantages of the dc motors?
for what purpose the star point is done in ct
how is calculated the quantity of weight in hot test xlpe?
How to discuss the phase shift of transformer considering open delta?
There is air in a room . the top and bottom of the room are at constant temp. T1 and T2. DRAW THE temp profiles if a. T1 greater than T2 b. T1 less than T2
How to measure the earth resistance value in a concrete pavement(flood light area)?
What is the efficiency during maximum power transfer?
Draw the equivalent circuit of crystal oscillator?
When semiconductor fuse does save thyristor in each cycle of conduction? Why under voltage setting keep less in SPRS and more in DC drive?
what kinds of Transformer oil grade is better for power transformer ?