what is scan time of PLC & in which factor scan time is
decide
Answers were Sorted based on User's Feedback
Answer / mprajaneb
Scan time depends on PLCs. In the timing diagram of PLC
execution we have three different times.
1. Input scan time
2. Execution time
3. Output scan time.
Input scan time the PLC receiving the data status from the
input peripherals.
Execution time is the time required to execute the program
or for scanning the rungs in PLC program.
Output scan time is the time required to send the results
to the output devices as per the execution of the program
rungs.
| Is This Answer Correct ? | 14 Yes | 1 No |
Scan time vary based on PLC models. Scan time means scannin
of ladder rungs in PLC program ( ONE time) for all the
rungs.
| Is This Answer Correct ? | 5 Yes | 4 No |
Answer / sanjana singh
scan time in plc is 10ms.
it depends on the length of programme.
| Is This Answer Correct ? | 0 Yes | 2 No |
If auto trip is operated, can you close the breaker.
what is the role of transistor in Circuit?
How the PF control while running DG set with load
what are different types of excitation in synchronous generator,what is the difference between them
i have 28/32 MVA power transformer with 11/6.6 KC voltage rating and 12%impedance.it have star connection at both side.but it have another thied winding tertiary winding.what is used of this winding. pl tell me
What is the work of ACCP in LT panel?
What happens on the secondary of a 33kV/11kV when one phase of the primary fuse blows?
What is the basic principal, by which DC voltage level is increased more than the supplied AC voltage during conversion. As upto AC level it is contorrled by firing anlge but after maximum level how is it possible.Please clear picture. OR we have to supply the higher level AC?
why do we connect voltmeter in parallel,why not in series,and why do we connect ammeter in series why not in paprallel...
What is the HVDC Transmission System? What are the conditions applicable to lay an HVDC Line?
reason behind why the reverse power relay of incoming machine was not acted even when no load was shifted on incoming machine after synchronising the machines ?
How to calculate 33 kv panther conductor line losses.
1 Answers Construction, Orange,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)