what is scour depth $ what's the process to determine it?
Answer Posted / sumanthteja
Bridge scour is the removal of sediment such as sand and
rocks from around bridge abutments or piers. Scour, caused
by swiftly moving water, can scoop out scour holes,
compromising the integrity of a structure.
Bridge scour is one of the three main causes of bridge
failure (the others being collision and overloading). It has
been estimated that 60% of all bridge failures result from
scour and other hydraulic-related causes
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
what is the use of beam end forces while using a staad ? wha they are show
How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.
dialation means
Describe a time when you anticipated potential problems and developed Preventive measures
What is high adherence steel bar? I have a general specification which refers to High Adherence steel bars, coils and meshes to BS EN 10080 and BS 4449 or BS 4483. Is this just general re-bar or is there something different about it? The spec originated in France.
what is the calculation of raw material for 0.35cum of m-15
What are the advantages and disadvantages of using plastic and timber fenders?
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
What is the release of lien?
Name the main components of a cad gui?
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)
What is the basic difference between OPC