Cemen-1 Fine agr.-2 Core agr.-3 calculate for per 100 qube feet (qubic feet wise)..

Answer / engr saleem mughal

Total Quantity=100 Cft
Dry Material for 100 Cft=154 Cft
Ratio=1:2:3
Sum=6
Cement=1/6*154=25.66 Cft
Sand=2/6*154=51.33 Cft
Crush=3/6*154= 77 Cft

Is This Answer Correct ?    3 Yes 0 No

Cemen-1 Fine agr.-2 Core agr.-3 calculate for per 100 qube feet (qubic feet wise)..

Answer / rajeshkerai

example using m3 for 100m3

1:2:3 for 100 m3
1+2+3= 6
cement: 1/6*100 = 16.67 m3
Sand: 2/6*100 = 33.33 m3
Aggregates: 3/6*100= 50 m3

therefore cement =16.67*1600(density of OPC)
= 26672kg/50=534bags)
sand = 33.33* 1400 (density of sand)
=46662kg/1000= 46.66tons
Aggregates= 50*1200 (density of aggregates)
=60000kg/1000= 60 tons

now add 40% for shrinkage
cement 534*40%= 213.6 TOTAL= 214+534= 748 bags
sand= 46.66*40%= 18.664 TOTAL= 46.66+18.66= 65.32tons
Aggregates= 60*40%= 24 TOTAL 24+60=84 tons

Is This Answer Correct ?    2 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer

0 Answers  


how many 1st class bricks in 1cu feet?

28 Answers   ECCI, Jayant Group, L&T,


what do u mean by shear?and tension?

6 Answers   L&T, Shoba Devlopers,


How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....

0 Answers  


How to plan a project

0 Answers   Ahluwalia Contracts, SDS,






which type of binding wire gauge using gulf countries

2 Answers   Al Rashed,


please briefly explain calculating or estimating steel quantity for a RCC column?

0 Answers  


Meaning of m20 and m200 concrete

10 Answers   WBPSC West Bengal Public Service Commission,


As shown in IS 456-2000 minimum cement content is include fly ash?

3 Answers  


Previous IS steel code?Thanks.

2 Answers  


what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????

0 Answers  


what is the maximum percentage of crush sand in mix design.also what is the difference betweeen grite powder & crush sand.

2 Answers   TATA, Vastu Kirti Enterprises,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)