Cemen-1
Fine agr.-2
Core agr.-3
calculate for per 100 qube feet (qubic feet wise)
Answer Posted / engr saleem mughal
Total Quantity=100 Cft
Dry Material for 100 Cft=154 Cft
Ratio=1:2:3
Sum=6
Cement=1/6*154=25.66 Cft
Sand=2/6*154=51.33 Cft
Crush=3/6*154= 77 Cft
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
How many lbs are there in a yard?
How much of the strength of concrete comes from post- production curing?
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
How much material will consume for following specification water tank (9*7.5*6 feet)?
What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)
how i can tak Quantity of mortar in block work
What are the responsibilities of a construction manager?
what is the permanent solution applied for restoration of leaning tower of pisa?
IS code for Rolling Margin of steel
how clculate excavated or backfilling quantity by simpson's rule
Why are steel plates inserted inside bearings in elastomeric bearings?
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall