Cemen-1
Fine agr.-2
Core agr.-3
calculate for per 100 qube feet (qubic feet wise)
Answer Posted / rajeshkerai
example using m3 for 100m3
1:2:3 for 100 m3
1+2+3= 6
cement: 1/6*100 = 16.67 m3
Sand: 2/6*100 = 33.33 m3
Aggregates: 3/6*100= 50 m3
therefore cement =16.67*1600(density of OPC)
= 26672kg/50=534bags)
sand = 33.33* 1400 (density of sand)
=46662kg/1000= 46.66tons
Aggregates= 50*1200 (density of aggregates)
=60000kg/1000= 60 tons
now add 40% for shrinkage
cement 534*40%= 213.6 TOTAL= 214+534= 748 bags
sand= 46.66*40%= 18.664 TOTAL= 46.66+18.66= 65.32tons
Aggregates= 60*40%= 24 TOTAL 24+60=84 tons
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
Sir how to find cutting length for footing steel bars in the shape of "u"
Describe the various methods of concrete curing?
what is box type waterproofing and how it is exsiccated and what is the method of doing box type waterproofing
can i get civil engineering test papers.......?????
How to calculate the force on a column of three story building. What should be the base concrete height?.
how to calculate load bearing column
Why the finite element method is lower bound solution?
what is the formula to find the diagonal shape stirrups?
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
Stringer How many cm goes to landind
Differentiate first angle & third angle projection?
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
Formula of mid span bar
sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????
How much of the strength of concrete comes from post- production curing?