Double Busbar Scheme for outdoor switch yard system (132kv) step up power plant

Hi friends
1. in this system both busbars energized all the time.
2. what is the meaning of main BB and transfer BB,
3. step up transformer connect main bus bar all the time or both BB connected through DS switch .
4.bus sectionalization means ?

thank you.



Double Busbar Scheme for outdoor switch yard system (132kv) step up power plant Hi friends 1. in..

Answer / k.prakashchandra

When one line is connected to a BB ,the other is the transfer BB . You can energize both BB either independently or using bus coupler . Sectionalzation means splitting the bus bar into sections lengthwise

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

We use MCCB not MCB for motor starters because MCCBs has capablity to drawout the motor starting current which is 5-6 times the full load current of motor for 1sec. Then why we use SDF in starter panel means MCC panels. Pls reply if any one knows this answer.

1 Answers  


I AM INTERESTED TO WIND A 3 PHASE MOTOR HOW I CALCULATE TURNS, PITCH,AND WIRE SIZE FROM STATOR DIMENTIONS

0 Answers  


How does an oscillator differ from an amplifier?

0 Answers  


ohms law is applicable for dc or ac current or for both??? explain it berifly??

3 Answers  


What is a single phase autotransformer?

0 Answers  






15 suspects are rounded by the police and questioned about a bank robbery. Only one of them is guilty. The suspects are made to stand in a line and each person declares that the person next to him on his right is guilty. The rightmost person is not questioned. Which of the following possibilities are true? A. All the suspects are lying. B. The leftmost suspect is guilty. B only

2 Answers   TCS,


Why is copper a better conductor of electricity than aluminium?

5 Answers   AES,


what happens when ac supply is given to the dc motor and dc supply is given to the ac motor?

1 Answers   GATE,


What happen if we apply square wave or traiangular waveform voltage to the transformer primary winding instead of sinusoidal wave?

0 Answers  


what is the basic difference between synchronous motor,synchronous generator and induction motor

7 Answers   NHPC, NTPC, Sail,


During Load testing of battery charger with temporary AC Generator .When reach 70% load Generator immediately shutdown .we could not able to Recognize ,what is exactly problem .Please kindly clarify us

1 Answers  


Why Two Transformers aside shoud be supperated by concreted wall?

5 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)