How to Calculate the amount of Cement mortor required only for 12 or 10 mm bonding? I mean to know only the amount of mortar for bonding not for plastering. Help me to find this.
Answer / nadim abdulgafur shaikh
its 33% of total brick or blockwork
| Is This Answer Correct ? | 0 Yes | 0 No |
Calculate no of brick req 230cmx115cmx100cm
what is BOQ? BOQ IS US IN ESTIMATE
What is the difference in Cement content for M-20 Concrete if y ou use OPC & PPC? What is the difference in the Curing Period?
If u want ur Ans.Of any Question so mail me skatiyar011@yahoo.in
TWO EXAMPLES OF NET WORT REVENUES FROM BUILDING CONSTRUCTION
A lorry contains 3-Units of material(Sand/Metal/Gravel...) so 3-Units means how many (CFT and M3)
which is the cheapest type of temporary flooring(say for using 6 months on)?
what is the compressive strenth of m30 grade cocrete column at 7 days
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
0 Answers APGenco, Emaar, Madhucon,
wat is six sigma course ? is it good for civil engineers . wat is pmp certification ? is it good for civil engineers .
how much weighs a square feet of slab of 5 inches thick
1:4:6 grade 15.84cum and how much cement and sand aggricate are used
1 Answers Minartech Developers,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)