Sir, my yokugava FF TYPE LEVEL transmitter us bad, i don't have spares available, i want to replace it with a Rosemount FF transmitter, please tell me what procedure to be followed and what changes to be done in dcs part.



Sir, my yokugava FF TYPE LEVEL transmitter us bad, i don't have spares available, i want to rep..

Answer / rajesh.

If the device calibration range is alike, and all required instrument data are match, we can use. We need to change instrument details like model#, serial#, make etc. in DCS engineering station. Upload, and down load data to communicate it online. And proceed to check as LEVEL both side in field as well as in DCS panel.

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Instrumentation Interview Questions

why 8bit microprocessor referred as 2^16?

2 Answers  


how many types 0f thermocouples?

6 Answers   HZL,


What should be the ideal tapping location for pressure differential transmitter for liquid service. If the tapping taken from the top of the pipe then PDIT will work properly or not. If PDIT do not work properly then what minimum corrective action should be taken in order to solve wrong tapping locations.

1 Answers  


how the flow rate is measured from a pipe with the help of pressure?

1 Answers  


why I need valve guard and whats different between guard and positioner ??

0 Answers  






can install leveltrol in steam drum for measurment the level of steam drum? if not then why?

1 Answers  


what do you mean by CJC (cold junction compensation).?

5 Answers   Jindal,


What is the Difference between CNC and PLC

1 Answers  


what is the difference between DELTA-V & FOUNDATION FIELD BUS

4 Answers  


sir, i preparing hpcl,ongc,barc,hal exams(instrumentation engg)pls send a placement papers

2 Answers   BARC,


Q1: Consider part of a control loop, which excludes the transmitter, consisting of a process, a controller and a control valve which may be represented by two dead times of 0.5 min each and three exponential lags of 0.8 min., 1.0 min. and 1.5 min. respectively. We wish to express this system as an overall first order plus dead time (FOPLD) model ie gain, time constant and process dead time. (We will see later that this is often done, to simplify controller tuning). For this exercise, gain is considered to be 1.0. (A) If the transmitter is a flow transmitter whose behaviour can be described by a dead time of 0.2 min. and an exponential lag of 0.5 min. in terms of the overall dead time and overall first order lag how can the system behaviour be approximated ? Overall dead time = Overall time constant = (B) If the transmitter is a temperature transmitter with a temperature sensor in a protecting well whose behaviour can be described by a dead time of 0.7 min. and an exponential lag of 15 min. how can the overall system behaviour be approximated now? Overall dead time = Overall time constant =

0 Answers  


What is instrumentation amplifier?

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)