calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum
Answers were Sorted based on User's Feedback
Answer / vikas d v
For 1cum ratio is 1:2:4
Adding 40-50% for wet concrete=1.5cum
VOL=1.5/(1+2+4)=0.214cum
cement=(0.214*1*(1440/50))=6.42bags
sand= 0.214*2=0.42cum
ca=0.214*4=0.856cum
| Is This Answer Correct ? | 15 Yes | 0 No |
Answer / sahilshah.civil@gmail.com
Cement : 6.6 Bag/Cu m
Sand : 0.51 Cu m/Cu m
Metal I & II : 0.98 Cu m/Cu m
| Is This Answer Correct ? | 7 Yes | 0 No |
Answer / rajasekhar
C.A = 0.92
Sand = 0.46
Cement = 0.23
Cement = 0.23 × 1440 = 331.2 Kgs = 6.624 bags ~ 7 bags.
Sand = cement × 2 = 331.2 × 2 = 662.4 kgs
C.A = cement × 4 or
Sand × 2 = 662.4 × 2 = 1324.8 kgs
| Is This Answer Correct ? | 6 Yes | 1 No |
Cement=1.57 x 1/(1+2+4)=0.23 m3
0.23 x 1440=331.2 kgs /50= 6.624 bags,
sand = 1.57 x 2/(1+2+4)=0.45 m3
CA = 1.57 x 4/(1+2+4)=0.90 m3
| Is This Answer Correct ? | 2 Yes | 0 No |
How do you calculate the unit weight of concrete?
what is the diffrence between grade beam and plinth beam
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
what is the minimum grade of concrete used in rcc(reinforced cement concrete)
8 Answers Lok Sewa Aayog, Prestige,
i am also applied for the AAI jr executive (CIVIL) written test. pls forward me the syllabus & test pattern if any question papers, any one got reply for this quaries? if ANY ONE KNOW THE DATES OF WRITTEN EXAM PLZ TOLD ME. dreamyagrawal@yahoo.com
2 Answers AAI Airports Authority Of India,
what is difference between design mix and nominal mix,where the design mix is used?
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
What is Rodding?
if the slab is 2 way then,where we will put lapping upper and lower side?means near to beam or center and near to center?
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
sometimes, in a column, reinforcement is provided equally on 2 sides and sometimes on 4 sides.what will be the difference in the method of designing?
Diagonal check is required for a layout work to confirm ––
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)