calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum
Answer Posted / vikas d v
For 1cum ratio is 1:2:4
Adding 40-50% for wet concrete=1.5cum
VOL=1.5/(1+2+4)=0.214cum
cement=(0.214*1*(1440/50))=6.42bags
sand= 0.214*2=0.42cum
ca=0.214*4=0.856cum
Is This Answer Correct ? | 15 Yes | 0 No |
Post New Answer View All Answers
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
What is meant by cartesian coordinate system?
5. Do you feel that your present employer estimates your full work potential? Are they pleased with your work performance?
how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????
what is right & short method of measurement of slab&beam
What is the difference between chamfer and fillet?
What will be weight of 0.5mm GI sheet per sq.ft?
How foundation is designed, Column design and beam design
Define What does civil status mean?
what is differences between ferrock and concrete ?
hi guys what happens if you are absent for a supplymentry exam?
CAST EFFECTIVE WATER SUMP CONSTRUCTION DETAIL
Explain what is alternate bid?
how to calculate the size of triangular ring in rcc column?
why do we provide haunches in rcc box or underpasses?