calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum
Answer Posted / vikas d v
For 1cum ratio is 1:2:4
Adding 40-50% for wet concrete=1.5cum
VOL=1.5/(1+2+4)=0.214cum
cement=(0.214*1*(1440/50))=6.42bags
sand= 0.214*2=0.42cum
ca=0.214*4=0.856cum
| Is This Answer Correct ? | 15 Yes | 0 No |
Post New Answer View All Answers
within an emergency scenario what are the safe systems of work a coss can setup as part of is duties
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.
How to get MEP technical,instaaltion & testing data for interview?
What is the purpose of the gap in the road on this bridge?
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
What is soil enforcement?
How many % we consider for lap for reinforcement for estimates
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
how do you stabilize a waterlogged area in road construction
calculate the quantity of water for 1:6 cement mortar
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
what is E
What is the development length given in pile?
Explain why concrete barriers have curved surface profiles?