calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum
Answer Posted / rajasekhar
C.A = 0.92
Sand = 0.46
Cement = 0.23
Cement = 0.23 × 1440 = 331.2 Kgs = 6.624 bags ~ 7 bags.
Sand = cement × 2 = 331.2 × 2 = 662.4 kgs
C.A = cement × 4 or
Sand × 2 = 662.4 × 2 = 1324.8 kgs
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
For what building Built-on balconies are preferable? What are the advantages?
afe or not
what is mean by c32/40s concrete class
What will be the exam pattern and syllabus for j.e post of haryana staff selection commision? Advt no. (02/2015) Some people says it would only be objective type question papers while others say it would be same as ssc (1 objective,1 conventional) ?? Please answer this question it is needfull to all.
in design case of structural member best suitrable percentage of steel limit is what
what is the weight of 12mm aggregates?
What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
Volume of 25kg putty bag & 40 kg putty bag volume??
define the strength
What is the crank length in the slab?
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
what is diffrence between catchment area,watershed and basin?
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
How long does it take concrete to harden?