Answer / hitenpatel
1m =3.281ft
1 sqm= 10.765 sq ft
1 cum= 35.3198 cu ft
1 brass= 100 cu ft
therefore 1cum=0.353 brass
| Is This Answer Correct ? | 501 Yes | 47 No |
Answer / er. rajasaheb borale
one cubic miter=1*1*1 i.e 3.281*3.281*3.281=35.31cuft.
one brass =10*10*1=100 cu ft
so one cumtr =35.31/100 =0.353 brass
| Is This Answer Correct ? | 148 Yes | 14 No |
Answer / kunal
1 mtr = 3.28 ft.
1 brass = 10*10*1 = 100 cum ft.
1 cum mtr = 35.28 cum ft.i.e 3.28*3.28*3.28.
1 brass = 35.28/100 m3 = 0.3528 m3
| Is This Answer Correct ? | 16 Yes | 6 No |
Answer / kunal
1 m3 = 3.28*3.28*3.28 i.e 1 m= 3.28 .ft
1 brass = 10*10*1 cu.ft
so 1 cu. mtr = 35.28/100 = 0.3528 brass
| Is This Answer Correct ? | 10 Yes | 5 No |
Answer / anil rathod
1m=3.28 feet
1m2=10.76 feet
1m3= 35.29 feet
Area = Breath*Height
Volume =Breath*Width *Height
| Is This Answer Correct ? | 6 Yes | 1 No |
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
what is c4x light weight cement blocks
Why do we not deduct steel volume to find actual volume of concrete in practical as we have studied that,,, actual volume of concrete = volume of column- volume of steel pls explain with reference of IS code?????
What is the ratio of M40 Concrete?
.5Ast
different types of rcc slab
what is the functional requirement of cement plaster in RCC members & masonry?? Is it Manditory to do plastering on all RCC members(beams, Columns, Slabs)? in what places plasterring could be kept as an optional one???
How much qty. of cement used for laying 1 Sq.Meter of tiles(600mmx600mm)
specific gravity of sand, coarse aggregate, cement.
for concrete cubes samples.. what if the 7 days gain the strength of 42.34 mm/2 and the 28 days only gain the strength of 37.5 mm/2?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)