While calculating quantity of cement required for 1 qubic meter
If mix is m25 1:1:2 =4
1.52/4=0.38, 0.38x1440=547.20 kgs
I know 1440 is unit weight of cement
And what is 1.52 ?
And some one using 1.54 and 1.53 etc...
Why they are using can u explain me what is 1.52, 1.53, 1.54?

Answers were Sorted based on User's Feedback



While calculating quantity of cement required for 1 qubic meter If mix is m25 1:1:2 =4 1.52/4=0.38,..

Answer / xyz

54 or 52 is the total % of dry ingradiants added..dry volume + wastage is included in it.for eq. for casting of 1 qm. of concrete volume..54 ,% of 1 m3 ingradiants added in batching..

Is This Answer Correct ?    1 Yes 0 No

While calculating quantity of cement required for 1 qubic meter If mix is m25 1:1:2 =4 1.52/4=0.38,..

Answer / muhammad bilal

this is the dry density of concrete(1.54 CUBIC METER)

Is This Answer Correct ?    1 Yes 0 No

While calculating quantity of cement required for 1 qubic meter If mix is m25 1:1:2 =4 1.52/4=0.38,..

Answer / ramadurai

1.54=1 m3+w/c 0.54=1.54 m3

Is This Answer Correct ?    1 Yes 1 No

While calculating quantity of cement required for 1 qubic meter If mix is m25 1:1:2 =4 1.52/4=0.38,..

Answer / mahaboobbasha

1.54 is the dry weight of aggregate

Is This Answer Correct ?    1 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

How to calculate the Qty of Mortar in 1 m3 Brick work? Detailed Calculation Required?

4 Answers  


what is unit weight of steel

11 Answers   RRB,


What is thickness of RC hume pipes of size, 300mm, 450mm,600mm

1 Answers   L&T,


Do you know differenence between design mix and nominal mix?

8 Answers   L&T,


What is the difference between dumpy level and auto level.

1 Answers  






Niti Aayog has recently chalked up an action to help India achieving _____ medals in 2024 summer Olympics after dismal performance in 2016 Rio Olympics? A)20 B)30 C) 40 D)50

1 Answers   HPSSSB,


if rise and tread of stairs rae 16 & 25cm with landing slab of thickness 100mm . If there are 8steps, and carpenter ask for to mark the bottom of centering of landing on column, what will be the height above floor finished level?

2 Answers  


what is coping?

11 Answers   GKC Projects Limited GKCPL, Technical Construction, Vijai Electricals,


what will happen if one could not properly follow the spacing of slab reinforcement bar?

0 Answers   Yirgalem Construction,


clear cover means the distance between main bar outer face to shuttering face. Is it right?

4 Answers  


if size is 235cmsx15cmx100cms so how many cement bags and how many sand bags are used for concrete mix

0 Answers   Ras Engineering, UltraTech,


How Many Brick in One Cubic Meter.

9 Answers   TUV,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)