Answer / sunil khairnar
(L+2B)-2C Where, L=overall Length, C= cover.
B=Bearing.(where given)
For Hook,Bend,oveplap,additional formulae should be use.
| Is This Answer Correct ? | 26 Yes | 12 No |
Answer / golam mustafa biswas
Total length-t.cover-2d(per bending)=cutting length
| Is This Answer Correct ? | 0 Yes | 1 No |
how many cement bags in 1m^3 cement concrete in all grade
why we do multiply 1.54 for dry volume of concrete?
in 1:2:4 concrete, spcify 1,2 and4 as towhat they indicate?
pl.may i place dry mix in casting of drain bed partialy filled with water?if no pl explain.
what is the m20 grade concrete ingredients?
What is zoning permit?
technical name of shuttering plywood
is it correct method to use crush sand in concrete as per is code
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
0 Answers Amit Enterprises, ICT,
Dear Sir , I have my diploma in civil engineering in distance mode, so can i do my B.teck in regular stream . kindly suggest Regards Ramakrishna
we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?
Allowable wastage for ready mix concrete?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)