While calculating quantity of cement required for 1 qubic meter
If mix is m25 1:1:2 =4
1.52/4=0.38, 0.38x1440=547.20 kgs
I know 1440 is unit weight of cement
And what is 1.52 ?
And some one using 1.54 and 1.53 etc...
Why they are using can u explain me what is 1.52, 1.53, 1.54?

Answer Posted / ramadurai

1.54=1 m3+w/c 0.54=1.54 m3

Is This Answer Correct ?    1 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)

1663


Which is the latest version of solidsworks?

732


What is the different type of slump test indications?

676


how is the reinforcement is distributed in triangular slab

1769


Why steel rods are produced only in even dimensions?

2163






How do You Maintain a structure after getting cube test of low strength.

1833


I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations

1037


what is mean by c32/40s concrete class

1336


1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...

1637


How to check slab shuttering level.? Or check list for slab ?

4071


A sieve analysis results in 100% retained in no. 50 Sieve, the fm is?

778


Why Is Propping Required For Long Structures Once The Form Work Is Removed?

702


how to design and calculate materail quantity for concrete speedbreaker ?

5392


cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com

1745


400 ku d/c clearess ketan hota hai?

1565