Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how to calculate quantity of concrete volume of pile with bulb
 



how to calculate quantity of concrete volume of pile with bulb  ..

Answer / somanathan

3.141*r*2*h
1000mm dia pile depth is 15meter

3.141*0.500m*0.500m*15m =11.778 cubic meters

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

What is diversion tunnel in a dam?

0 Answers  


9*9m 1:4:8 ratio using what quantity of 40mm aggregate, sand&cement please tell anwser

3 Answers   L&T,


how much solid block in 1m3

8 Answers  


koi bta sakta ha ka steel ko calculate krna ka full mathod pls

4 Answers  


How to calculate cement qty of M10, m20, m25 ? I got the formula but I lost it.

3 Answers  


what is the ratio of M10,M20,M30,M40,M50,M60 grade concrete

28 Answers   NCC, PWD, SPML, Student,


what will be the quantity of following materials in P.C.C for the total area of (100'x70'x 0'4") 1)NO. OF CEMENT BAGS 2)SAND IN CU.FT 3)METTLE IN CU.FT

0 Answers   Pratibha Industries,


How to calculate chejja reinforcement

0 Answers   Grow Homes,


What are the advantages of Prestressed Concrete

4 Answers  


The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?

0 Answers  


7500 liters capacity of water tank find the inner Length L = ? Breadth B = ? Depth D = ? in feet

3 Answers  


my client's 10 year old building have been affected by the neighbor new building construction with out set back.Old building cantilever bldg hanged by 3". It is supported by introducing 2 rcc columns & beams.Now how to conceal the cracks?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)