Answer / sjtbehera
According to IS code In acolumn minimum height of casting
is 1200mm or 4' (apporox)
| Is This Answer Correct ? | 18 Yes | 4 No |
Answer / kamlesh chauhan
we can not caste any ht more than 2.4 mt at a time,you can
caste only 2.4 mt ht at a time,because vertical drop of
concrete should not be more than 2.4 mt due to seggregation
problem.
| Is This Answer Correct ? | 17 Yes | 9 No |
Answer / ajeet kumar bhatnagar
As per IS. concrete should not pour more than 1.5mtr hight
but if you are pouring by pump using hose pipe you can fall
concrete up to 1.5mtr height and col.up to 3.0 mtr. height
can be casted.
| Is This Answer Correct ? | 10 Yes | 2 No |
Answer / ajeet kumar bhatnagar
As per the I.S.code concrete should not pour greater than
1.2 mt heigh. But if u are using hose pipe then u may cast
as per the lenth of hose pipe reaches in side of col,which
also maintains I.S. specification of 1.2 mtr heightpouring
Thus we can cast col. more then 1.2 mtr. height. Generaly
hose pipe may be inserted up to 2.0-2.5 mtr depth in col.
and we can cast up to 3.7 mtr height of col.
| Is This Answer Correct ? | 5 Yes | 0 No |
Answer / jhulzkee
1.5m since the max drop of concrete should be 1.5m height
to avoid seggregation of aggregates.
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / girish rawat
you can cast up to 4 mts of column if you have reqd
supporting system for the same. As for the IS you cannot
pour concrete more than 1.5 mts as segregation and self
compaction takes place. For the columns you there is no
issue as the concrete doesn't drop to the bottom at once. it
is interrupted by stirrups all the way.
This is based in practical experience and we have got it right.
Secondly nowadays there is Mivan Shuttering where you cast
the entire slab and column at one stroke.
Keep moving with new technology, you will save time and the
quality will be better if the mix is homogeneous lesser joints
| Is This Answer Correct ? | 4 Yes | 3 No |
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
in design case of structural member best suitrable percentage of steel limit is what
why we use cement for concrete
Formula of mid span bar
0 Answers Modern Construction Company, PFPL,
What are new technologies in civil engr. that can reduce construction cost?
For Granite Flooring,For Cement Slurry purpose which one is effective of cost control whether OPC or PPC or White cement?
How to calculate cement, aggregates for any one grade of concrete for icum?
1 Answers Megha Constructions, MEIL, Student,
what is the specific gravity of rubble in plum concert
how we can calculate the quantity of sand & cement & also Aggregate so give me to this answer for a slab Length is : 25' /3.28 = 7.62 Mtr Width is : 30' /3.28 = 9.14 Mtr Depth is : 0.6"/3.28 = 0.15 2Mtr
what is periode of deshuttering for different area of slab
Why is cover provided in beams, slabs, lintels, columns, etc ? What is the drawback of not providing cover in the same?
what is the difference between NP2 Class and NP3 Class RCC Hume pipes
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)