How many bages of cement used in 1cft?and how we calculat sand and agregats
Answers were Sorted based on User's Feedback
Answer / sfz ans
M20 (1: 1.5: 3)
Wet mix = (Dry mix)x 1.52 ie: 52% more
Cement = [ 1/(1+1.5+3) ]x 1.52 = 0.2763cum
ie: 0.2763cum/1cum conc
ie: 0.2763cum/35.25cft conc
ie: 0.00783 cum/cft conc
ie: (0.00783/.0347)bags = 0.2258 bags = 0.2258 x 50 = 11.29kg
Therefore
Sand = 11.29 x 1.5 = 16.941 kg
Agg = 11.29 x 3 = 33.87 kg
Note: But Concrete is always estimated in cubic meters.
| Is This Answer Correct ? | 14 Yes | 3 No |
Answer / madhusudhan reddy
1.25 CFT = 50 KG = 1.0 BAG OF CEMENT
1.00 CFT = 40 KG = 0.8 BAG OF CEMENT
| Is This Answer Correct ? | 13 Yes | 6 No |
Answer / sfz ans
http://theconstructor.org/practical-guide/estimated-quantities-of-materials-required-per-cubic-metre-of-compacted-mortar-or-concrete/1304/
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / sumit
for 1 cubic meter (1:1.5:3)
1/1:1.5:3*1.52*28.8=6.4bags of cement
sand 6.4 *50*1.5= 480 cu ft
agg 6.4*50*3=960kg
| Is This Answer Correct ? | 3 Yes | 2 No |
Ratio for concrete M20 equal is 1,1,2
Total volume equal is 1cft
Concrete dry volume equal is 1.52
Cement bags= 1/4*28.8*0.028*1.52 equal is 0.306 bags
= 15.32 kg cements
Sand equal is 1/4*0.028*1.52 equal is 0.170 Cum
= 0.375 cft sand
Agregats equal is 2/4*0.028*1.52 equal is 0.021 Cum
= 0.751 cft agregats
| Is This Answer Correct ? | 3 Yes | 7 No |
How manu days after the casting of a slab another slab can be casted above it? what is the total curing time of a slab if ponding is not done on it?
Difference between wbm and gsb in road construction
4 Answers CPWD, GSB, Ircon, JMC Projects, L&T, RD,
waht is the angle of reposae
how to calculate the quantity of cement,sand and aggregate when the ratio of mixing is 1:2:3
0 Answers Ajnara Group, Assosa University,
granite tiles laying 60/sq ft.how to convert in sq mt,what is the mltiplying value.
what are the code used for residental building?
how to control PQI (Project Quality Index)
How to calculate the dia of reinforcement when required (as per drawing) dia of reinforcement steel not available at site?
3 Answers MNC, N J Devani Builders, Simplex,
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?
What are the joints wants to made in masonry where door opening, arches like etc..
what is main diffrence between vitrified and cremic tile????
2 Answers Colliers International,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)