How many bages of cement used in 1cft?and how we calculat sand and agregats
Answer Posted / sfz ans
M20 (1: 1.5: 3)
Wet mix = (Dry mix)x 1.52 ie: 52% more
Cement = [ 1/(1+1.5+3) ]x 1.52 = 0.2763cum
ie: 0.2763cum/1cum conc
ie: 0.2763cum/35.25cft conc
ie: 0.00783 cum/cft conc
ie: (0.00783/.0347)bags = 0.2258 bags = 0.2258 x 50 = 11.29kg
Therefore
Sand = 11.29 x 1.5 = 16.941 kg
Agg = 11.29 x 3 = 33.87 kg
Note: But Concrete is always estimated in cubic meters.
| Is This Answer Correct ? | 14 Yes | 3 No |
Post New Answer View All Answers
how to take concrete quantity for precast segment for viaduct project?
Pls explain me about tension and compression in a flat slab
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM
what is differences between ferrock and concrete ?
In case if concrete box girder bridges how is the number of cells determined?
How do we calculate absolute pressure?
How much 1 cum of M15, M20 & M25 concrete weigh?
What are the different softwares used for cad?
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
How many % we consider for lap for reinforcement for estimates
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Describe the various methods of concrete curing?
rate analysis for cement pointing 1:4 , for 100 sq m
acceptance criteria for concrete works