what is the problem not getting 7 days slab cycle in Mivan
formwork? what is the output of mivan carpenter per day?
Answers were Sorted based on User's Feedback
Answer / er nitin lahane
Per day work for 1 carpenter is minimum 10 sqm per, I.e your shuttering area is 3250sqm you completed work in one day you are required 325 carpenter.you complete work in 8 day you required 40 carpenter per day. Ok
| Is This Answer Correct ? | 2 Yes | 0 No |
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
when we select buildup beam
Quantity calculation
how to check the quality of concrete
wat is the quntities of cement and sand for 10msquer wii plastering for 10mm tick
plz tell me the most used units and their conversion in civil engg?
What is the compressive strength of fly ash bricks?
Grades of concrete
28 Answers Mittal Steel, UNOPS,
What are the different theories of failure under static load?
hai,i completed my b.tech civil.Recently i wrote the appsc exam for managers water supply engg.I want answers for general studies and civil engg paper2.If any body know or written that exam send to my mail id is ruksana.sk08@gmail.com.
What is the difference between opc cement to ferro cement
How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)